Settings
Program configuration for HTP North Corridor
Assessment standard
Impact assessment method
Default transport distances
| Road, articulated 32 t | 82 km |
| Rail freight | 410 km |
| Barge, inland waterway | 168 km |
| Spoil haulage to licensed fill | 24 km |
Cost defaults
Default discount rate3.5% real
Default study period60 years
Escalation indexENR CCI
Shadow carbon price$145 per tonne
Biogenic carbon treatment
Module D treatment
Audit note. Methodology locked by Priya Nair on 02 Jun 2026. Changes require program lead approval.