Unit rates by work item. Rates escalated to Q3 2026 using ENR CCI.
Unit rates by work item, region and source
ItemCategoryUnitRateRegionSourceLast updatedVersion
Precast segmental lining, C50/60, erectedTunnellingm3$1,284.60US-NY MetroBenchmark, HTP 202502 Jul 2026v14.2
Reinforcement bar, supply and fixStructuralt$2,146.00US-NY MetroSubcontract quote02 Jul 2026v14.2
Shotcrete primary lining, sprayedTunnellingm3$742.30US-NY MetroBenchmark, HTP 202518 Jun 2026v14.1
In-situ concrete, C40/50, placedStructuralm3$318.75US-NY MetroRSMeans 202602 Jul 2026v14.2
Structural steel, fabricated and erectedStructuralt$4,912.00US-NY MetroSubcontract quote24 Jun 2026v14.1
Bulk excavation, spoil to licensed fillEarthworksm3$41.20US-NY MetroRSMeans 202602 Jul 2026v14.2
Ductile iron pipe, DN600, laid and jointedUtilitiesm$684.90US-NY MetroSupplier schedule11 Jun 2026v14.1
Ballasted track, 60E1, installedTrackm$1,872.40US NationalBenchmark, HTP 202502 Jul 2026v14.2
Sprayed waterproof membrane, 3mmTunnellingm2$68.15US-NY MetroSupplier schedule29 May 2026v13.9
Periodic maintenance, tunnel lining inspectionMaintenancekm per year$96,400.00US NationalHTP O and M model02 Jul 2026v14.2
Showing 10 of 10 rates.