Program: HTP North CorridorPackage: All (5)Scenario: BaselineBoundary: A1-A5, B, C, D reported separatelyDataset: EC3 snapshot 2026-07-14Method: EN 17472 / TRACI 2.1
Procurement
Carbon limits and evidence requirements written into tender clauses, set from the assessed baseline
Clauses issued
8
across five packages
Carbon capped
68%
of assessed embodied carbon
Product EPD required
5
of 8 clauses
Awaiting evidence
3
before award
Coverage against assessed carbon
Shadow carbon price $145 per tonne applies to tender evaluation
Capped by a numeric clause limit
68%
Evidence required, no numeric cap
14%
Not yet specified
18%
Limits are set at the assessed baseline for each material, so a tender that meets the specification reproduces the assessment rather than undercutting it. Unspecified materials are the tail below 1% of the total.
Specification clauses
Carbon limits and evidence requirements by specification clause
ClauseMaterialSpecificationCarbon limitEvidence requiredPackagesStatus
SC-24.1Precast segmental lining, C50/60Minimum 30% GGBS replacement, optimised segment geometry1,042 kgCO2e per m3Product-specific EPD, ISO 14025, valid at awardTU-03Active
SC-24.2Reinforcement bar, grade 500Electric arc furnace route, minimum 90% recycled content762 kgCO2e per 1,000 kgProduct-specific EPD plus mill certificateAllActive
SC-24.3In-situ concrete, C40/50Low carbon mix design, supplier to nominate binder394 kgCO2e per m3Product-specific EPD, regional to US-NYST-01, UT-01Active
SC-24.4Structural steel sections, S355Declared route, industry average accepted at tender2,310 kgCO2e per 1,000 kgIndustry average EPD accepted, product EPD preferredST-01In review
SC-24.5Bulk excavation and spoil haulageStage IV plant minimum, haulage within 24 km13.4 kgCO2e per m3Plant register and haulage log, monthlyEW-01Active
SC-24.6Ductile iron pipe, DN600Cement lined, declared transport route610 kgCO2e per mProduct-specific EPDUT-01Evidence pending
SC-24.7Crushed granite ballastLocal source within 120 km of railhead8.4 kgCO2e per 1,000 kgQuarry declaration and haulage recordTR-01Active
SC-24.8Sprayed waterproof membraneDeclared ozone depletion potential, no HCFC blowing agentsReported, no numeric capSafety data sheet plus EPDTU-03In review
Limits trace to the material factors on the calculation trace and the declarations in the EPD library. Changing a mapping changes the limit a supplier must meet.
NEXT STEP
Document Envision credits
14 of 18 credits evidenced