Skip to content
Program: HTP North CorridorPackage: All (5)Scenario: BaselineBoundary: A1-A5, B, C, D reported separatelyDataset: EC3 snapshot 2026-07-14Method: EN 17472 / TRACI 2.1
Scenarios
Create, compare and switch the assessment scenario driving every result page
Scenario builder
Toggle a lever to see the whole life impact move immediately
LIVE RESULT
Embodied carbon
184,620 tCO2e
At baseline
Whole life cost, NPV
$412.8M
At baseline
Cost of abatement
Where the reduction comes from
Select a lever above to attribute the reduction
050k100k150k200kBaseline: 184,620 tCO2e184,620BaselineResult: 184,620 tCO2e184,620Result
Levers are applied in the order listed, each against the running total. Deltas are independent, so this attribution ignores interaction between measures — the note on the saved scenarios below explains where that matters.
Saved scenarios compared by life cycle stage
A1-A3A4-A5BC
Baseline
A1-A3: 128,340 tCO2eA4-A5: 14,540 tCO2eB: 28,410 tCO2eC: 13,330 tCO2e
184,620
baseline
$412.8M
LC-Alt-1, GGBS 50%
A1-A3: 112,400 tCO2eA4-A5: 14,300 tCO2eB: 27,590 tCO2eC: 13,160 tCO2e
167,450
-9.3%
$418.3M
LC-Alt-2, GGBS 30% plus geometry
A1-A3: 107,640 tCO2eA4-A5: 13,540 tCO2eB: 26,950 tCO2eC: 12,960 tCO2e
161,090
-12.7%
$415.5M
Full package optimisation
A1-A3: 103,960 tCO2eA4-A5: 11,720 tCO2eB: 25,990 tCO2eC: 12,650 tCO2e
154,320
-16.4%
$424.6M
Extended maintenance interval
A1-A3: 128,340 tCO2eA4-A5: 14,540 tCO2eB: 26,900 tCO2eC: 13,330 tCO2e
183,110
-0.8%
$408.9M
Rev12 pre-optimisation
A1-A3: 141,060 tCO2eA4-A5: 14,540 tCO2eB: 28,410 tCO2eC: 13,330 tCO2e
197,340
+6.9%
$419.7M
Every saved scenario carries a full stage breakdown, not just a headline. The archived Rev12 case is retained so the improvement against the original design is auditable.
Saved scenarios
Selecting a scenario rebinds every result page and report to it
Saved totals come from a full recalculation run, so they capture interaction between measures. The builder above adds lever deltas independently and will differ slightly on multi-lever combinations.
Saved scenarios with carbon, cost and the levers applied
ScenarioStatusEmbodied carbonvs baselineNPVOwnerUpdatedAction
Baseline
As-designed reference case, BOQ Rev14 with OPC precast lining.
Baseline184,620
$412.8MPriya Nair14 Jul 2026, 09:42
LC-Alt-1, GGBS 50%
Fifty percent GGBS replacement across all tunnel lining segments.
GGBS 50% blend
Active167,450
-9.3%
$418.3MMarcus Adeyemi14 Jul 2026, 10:07
LC-Alt-2, GGBS 30% plus geometry
Thirty percent GGBS with optimised segment geometry, recommended option.
GGBS 30% plus optimised geometry
Active161,090
-12.7%
$415.5MMarcus Adeyemi14 Jul 2026, 10:07
Full package optimisation
All abatement levers applied together across the five packages.
GGBS 30% plus optimised geometryLow carbon station box mixElectrified plant fleetReduced spoil haulage distance
Draft154,320
-16.4%
$424.6MDana Whitfield13 Jul 2026, 15:22
Extended maintenance interval
Inspection and resurfacing intervals stretched under revised durability case.
Extended maintenance interval
Draft183,110
-0.8%
$408.9MRavi Krishnan11 Jul 2026, 11:40
Rev12 pre-optimisation
Superseded case retained for the audit trail.
Archived197,340
+6.9%
$419.7MPriya Nair02 Jun 2026, 08:15
NEXT STEP
Compare alternatives
Baseline against the two design options
Compare alternatives